Vantage Data Centers Frontier: $25B Texas AI Campus

Vantage will invest more than $25 billion to build Frontier, a 1,200-acre, 10-building campus totaling roughly 3.7 million square feet near Abilene, about 120 miles west of Dallas Fort Worth. The site is designed for ultra-high-density racks of 250kW and above, paired with liquid cooling for next-generation GPU systems. Construction has started, with first delivery targeted for the second half of 2026. Vantage expects more than 5,000 jobs through construction and operations. This is the company's largest project to date and underscores its acceleration beyond a global footprint of 36 campuses delivering nearly 2.9GW of critical IT load. Vantage is a portfolio company of Digital Bridge Group.
Vantage Data Centers Frontier: $25B Texas AI Campus
Image Credit: Vantage Data Center

Vantage Frontier: $25B Texas AI Data Center Campus

Vantage Data Center plans a 1.4GW campus in Shackelford County, Texas, framing the next phase of AI-era infrastructure at hyperscale.

Key specs: 1.4GW, 1,200 acres, 10 buildings


Vantage will invest more than $25 billion to build Frontier, a 1,200-acre, 10-building campus totaling roughly 3.7 million square feet near Abilene, about 120 miles west of Dallas-Fort Worth. The site is designed for ultra-high-density racks of 250kW and above, paired with liquid cooling for next-generation GPU systems. Construction has started, with the first delivery targeted for the second half of 2026. Vantage expects more than 5,000 jobs through construction and operations. This is the company’s largest project to date and underscores its acceleration beyond a global footprint of 36 campuses delivering nearly 2.9GW of critical IT load. Vantage is a portfolio company of DigitalBridge Group.

Why Texas: power, scale, ERCOT access

AI infrastructure demand is outpacing traditional data center development on power, density, and speed to market. Texas offers scale, land, and access to the ERCOT power market, plus a pro-investment policy climate. Training clusters tolerate longer-distance latency, so proximity to the DFW metro is less critical than power availability and build velocity. The location provides a path to massive capacity while easing pressure on constrained urban grids.

Economic impact for Abilene and Texas

Frontier will be an economic anchor for Shackelford County and the Abilene region via jobs, tax base, and local supply chains. Vantage plans local hiring, training programs, and scholarships for students over the lifecycle of the project. Statewide, the investment strengthens Texas positioning as a national AI infrastructure hub.

AI-Scale Design: Power, Density, Liquid Cooling

The campus blueprint is optimized for GPU-heavy clusters that push thermal and electrical limits beyond traditional cloud designs.

1.4GW capacity and 250kW+ racks explained

At 1.4GW of planned capacity, Frontier approaches the scale of a utility. Rack densities north of 250kW point to immersion or direct-to-chip liquid cooling and high-capacity power distribution. This is consistent with the shift to multi-megawatt GPU pods tied by low-latency fabrics and high-throughput storage tiers. It also implies advanced power topologies, larger electrical rooms, and robust harmonic filtering to handle non-linear IT loads.

Liquid cooling aligned to ASHRAE and OCP

Vantage will deploy liquid cooling to support next-gen GPU loads, which aligns with industry guidance from ASHRAE TC9.9 and Open Compute Project work on Advanced Cooling Facilities. Tenants should plan for warm-water loops, CDU placement, leak detection, and serviceability workflows. Hardware roadmaps should consider OCP and Open19 specifications, facility coolant compatibility, and lifecycle refresh cycles tied to 800G and 1.6T Ethernet transitions.

Delivery timeline (H2 2026) and project risks

First capacity lands in H2 2026, which is aggressive for power, cooling, and interconnection at this scale. Key risks include transformer and switchgear lead times, substation interconnect schedules, and liquid-cooling supply chains. Early design freezes and structured material commitments will be table stakes for on-time turn-up.

ERCOT Energy Strategy, Water Use, and ESG

Power procurement and resource stewardship will define both execution risk and tenant perception.

Grid interconnection, PPAs, and carbon hedging

ERCOT offers competitive wholesale pricing and fast growth in wind and solar, but interconnection queues and transmission constraints remain real. A multi-phase plan will require staged energization, likely with large on-site substations and long-duration PPAs or virtual PPAs to hedge price and carbon exposure. Tenants should seek transparency on capacity reservations, renewable matching, and hourly carbon accounting.

Water-efficient cooling and LEED targets

Frontier will use a highly efficient closed-loop chiller system with minimal water usage, which is critical in water-stressed regions. Vantage expects meaningful savings versus evaporative systems and is targeting LEED certification. For buyers with ESG targets, this reduces water intensity risk and supports reporting under frameworks like GRI and CDP.

Resiliency for long AI training workloads

AI training workloads have long run times and checkpointing overheads, so uptime and grid volatility matter. Expect N+ redundancy at scale, diverse feeders where available, and potential for on-site backup generation and energy storage. Tenants should validate fault domains, maintenance windows, and ride-through strategies across power events.

Network: Long-haul Backhaul, Interconnect, Optics

AI-scale campuses reshape regional transport demand and data center fabrics.

Long-haul and metro fiber growth to DFW

Frontier will drive new long-haul and regional fiber builds between Abilene and DFW and to other national interconnect hubs. Carriers and wholesalers will pursue diverse routes, regen sites, and protected services to meet multi-terabit requirements. Dark fiber and spectrum services will be in focus for hyperscalers and large AI tenants.

400G/800G waves and routed optical (ZR/ZR+)

Demand will shift to 400G and 800G wavelengths with open line systems and ZR/ZR+ pluggables in routed optical designs. Operators should plan for 400ZR today and 800ZR trials, along with flexible grid ROADM deployments. Time-sensitive training pipelines will benefit from deterministic latency guarantees and automated restoration policies.

Intra-campus AI fabric: 800G to 1.6T Ethernet

Inside the data centers, 800G Ethernet is mainstreaming with 51.2T switches, on a path to 1.6T and 102.4T systems. RoCEv2-based AI fabrics and improved congestion control will be critical for job completion times. Power and thermal budgets must account for higher-speed optics and the move toward linear-drive and co-packaged optics later in the decade.

Texas in the AI Data Center Triangle

Texas is consolidating its role alongside Northern Virginia and the Mountain West in the AI capacity race.

Policy advantage and ERCOT power mix

Streamlined permitting, access to ERCOT, and rapid renewable buildouts give Texas an execution edge. The policy stance is favorable to large digital infrastructure and ancillary investment in transmission and workforce development. This is attracting capital at a pace few markets can match.

How Frontier complements Vantage’s portfolio

Frontier complements Vantages ongoing build in San Antonio and a recently announced multibillion-dollar campus in Nevada, signaling a multi-region AI strategy. For tenants, this enables distributed training and disaster recovery patterns with regional diversity. It also supports proximity to major cloud regions without being inside congested metros.

Tenant considerations: training vs inference

Training, fine-tuning, and batch inference fit well in West Texas; latency-sensitive inference may still sit nearer to end users. A hub-and-spoke approachtraining at Frontier, inference near DFW and other metrosbalances cost, power, and performance. Cross-region bandwidth reservations and consistent security postures will be essential.

Next Steps and Buyer Actions

Procurement, interconnect, and sustainability details will determine how quickly this capacity becomes usable for AI at scale.

Actions for cloud and AI tenants

Lock in power-dense halls and liquid-cooling options early, with clear SLAs on rack density, coolant distribution, and service windows. Align optics and fabric roadmaps with facility timelines. Pursue granular renewable matching and transparent carbon reporting to meet internal targets.

Actions for carriers and fiber builders

Accelerate diverse long-haul and regional routes into Shackelford County and DFW, design for 400/800G services, and enable ZR/ZR+ at scale. Offer protected paths, spectrum services, and deterministic latency SLAs tailored to AI pipelines. Engage now on meet-me design and conduit rights.

Actions for enterprises and integrators

Evaluate colocation versus cloud GPU economics with 24 year runway assumptions, factoring in optics, networking, and cooling OPEX. Standardize on liquid-cooled reference architectures and plan for staged upgrades to 1.6T Ethernet. Build multi-site data mobility plans that harness Frontiers scale without locking into a single region.


Recent Content

The Istanbul Expo Center (IFM) has become Türkiye’s first venue to deploy an indoor 5G Private Network, turning its 96,000 m² exhibition space into a next-gen smart venue for digital trade fairs. The Opticoms and ADSYS project integrates IoT, edge computing, and network slicing to support real-time testing, secure enterprise connectivity, and immersive AR/VR showcases.
5G-Advanced is redefining mobile networks through AI-native intelligence, sustainability, and advanced capabilities like XR support, NTN integration, and low-latency industrial IoT. Built on 3GPP Releases 18–20, it enables predictive automation, 30% energy savings, and sets the stage for 6G.
Memphis Light, Gas and Water (MLGW) and Nokia have launched the first standalone private 5G network by a U.S. municipal utility. This $31 million investment will modernize infrastructure across Memphis and Shelby County, enhancing real-time monitoring, outage response, cybersecurity, and smart grid capabilities for over 420,000 customers.
Predicting AI’s future is difficult, but its impact on work and life is certain. Many organizations are hesitant, “nibbling around the corners” instead of embracing transformative applications. This slow adoption, however, has allowed us to better understand and utilize large language models. The AI revolution mirrors the steam engine transformation, with organizations needing to integrate AI to stay competitive. The biggest winners will be those that successfully integrate AI, gaining a significant advantage. The most significant transformation will be in knowledge management, how organizations make decisions and leverage collective intelligence.
Connected aviation is transforming airports with secure private networks, IoT, and real-time data. This article unpacks how smart airports boost efficiency, safety, and passenger experience while unlocking new business value with real-world case studies from Heathrow, Changi, Dubai, and more.
Connected aviation is reshaping airports into smart, seamless ecosystems inside and outside the terminal. This case study reveals how hubs like Changi, Schiphol, and SAN use private networks, IoT, and cross-team collaboration to improve passenger flow, airside operations, sustainability, and safety.
Whitepaper
Download our latest whitepaper, sponsored by RADCOM, to see how automated assurance, using the power of AI/ML, can help tackle these questions head-on....
Radcom Logo
Whitepaper
Download the Open RAN whitepaper to understand the parameters, challenges, and benefits of greenfield vs. brownfield deployments....
GSMA logo

It seems we can't find what you're looking for.

Download Magazine

With Subscription

Subscribe To Our Newsletter

Private Network Awards 2025 - TeckNexus
Scroll to Top

Private Network Awards

Recognizing excellence in 5G, LTE, CBRS, and connected industries. Nominate your project and gain industry-wide recognition.
Early Bird Deadline: Sept 5, 2025 | Final Deadline: Sept 30, 2025